forked from EduCraft/curriculum-project-hub
475 B
475 B
Prove the production release gate
Type: task Status: open Blocked by: 01, 02, 03, 04, 05, 06, 07, 09, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22
Question
After the readiness investigations and resulting fixes are resolved, can one repeatable release procedure prove build/test/spec health, deploy a clean production-like environment, exercise critical tenant and agent journeys, verify observability and recovery, and either roll forward or roll back safely?